Implementation of the concrete structure of the cooling tower
Implementation of the concrete structure of the cooling tower
Employer: Absan Energy Company
Scope of work: installation and implementation
Contractor: Amin Process Chemical Company
Location: Tehran Oil Refinery
Selected images
About the project
Construction and installation of an Open Circuit Cooling Tower unit with a design capacity of 6600 cubic meters including 4 cells each with a capacity of 1650 cubic meters per hour and a basin with a capacity of 1100 cubic meters.